Do a check list of all outstanding works and/or tasks and then do a programme and agree it with the Engineer. Be sure that the Engineer signs-off for every item completed in your checklist. Normally, the check list will involve outstanding works or punchlist items or any outstanding documentation like As-Built Drawings, O&M manuals, Warrantees, Training, etc.
Member for
15 yearsHi Daniel,Thanks for your
Hi Daniel,
Thanks for your valuable reply.
Regards
Sunil
Member for
24 yearsSunil,Do a check list of all
Sunil,
Do a check list of all outstanding works and/or tasks and then do a programme and agree it with the Engineer. Be sure that the Engineer signs-off for every item completed in your checklist. Normally, the check list will involve outstanding works or punchlist items or any outstanding documentation like As-Built Drawings, O&M manuals, Warrantees, Training, etc.
Hope this helps.
Regards,
Daniel