Mid project baseline issues

Member for

21 years 1 month

Adam

 

Glad I could help.

It is worth remembering the Planned Dates also determine where your Planned Value (BCWS) will profile to, which I have learnt to my cost over the 9 years working with Primavera!

 

Regards

James 

Member for

14 years 1 month

Thank you James that fixed it!

I displayed the planned columns, exported to excel and copied the start/finish dates over the planned and imported it back into P6. Now the baseline bars match the current bars just like I needed.

Thank you for this!

Member for

21 years 1 month

Hi

I am assuming you are baseling where you are now and so the baseline is to equal current?

 

Have you reviewed your 'planned dates' as if they do not match the start/finish dates at the time you baseline you will get a differance.

Add Planned Start and Planned Finish columns to your gantt chart and compare.

 

Regards

 

James

Member for

21 years 1 month

Hi

I am assuming you are baseling where you are now and so the baseline is to equal current?

 

Have you reviewed your 'planned dates' as if they do not match the start/finish dates at the time you baseline you will get a differance.

Add Planned Start and Planned Finish columns to your gantt chart and compare.

 

Regards

 

James

Member for

15 years 11 months

I understand that you selected The Primary Baseline Under the Name Column but the corresponding Bar on the timescale column was shown as Plan Bar.[[wysiwyg_imageupload:888:]]

Member for

14 years 1 month

Just checked and the bars selected are Primary Baseline and Baseline Milestones.

Member for

15 years 11 months

Adam,

On the Bars Window, make sure the timescale selected is Project Baseline Bar or Primary Baseline Bar  instead of Plan Bar.

 

Hope this will help.