Baseline Bars

Member for

22 years 10 months

Roland,

 

There are a dozen different answers to your question depending upon which software you are using.  I shall assume that you are referring to P6.  If that assumption is incorrect, then ignore the next paragraph.

 

The dates displayed at the ends of P6 baseline bars come from the Planned Start and Planned Finish columns.  These columns ‘float’ along with the activity’s Early Start and Early Finish dates until the activity registers an Actual Start.  At that point, the Planned Start and Planned Finish dates ‘freeze’.  Should the activity later show a progress situation other than the ‘frozen’ Early Finish date, one would observe that the baseline bars no longer match the early bar.  I hope that this helps.  Good luck!

Member for

14 years 6 months

Just put the sanpshot of your schedule to understand better. Shall answer your querry after that.

Member for

16 years 11 months

Hi Payawan 

You are correct it is due to updates you did in the first quater

Regards

Shahul

Member for

22 years 5 months

I m talking of the baseline bars of all the inprogress and completed activities that have a different bars.