Several Crews in Vico Control 2009

Member for

14 years 7 months

Conditonal Yes,

On the edit task/resources tab the crew composition is composed by you - so define it with two crews; after the crew is added then change the supplier from the supplier defined on the general tab to the 2nd crews supplier.

Member for

14 years 1 month

Hi Mike

 

No, by this way the program reduces the duration in each locations. I`ve learned another way: Spliting the task so you choice the locations for each "crew".

 

Best regards.

 

José Otávio

Member for

19 years 10 months

Hi Jose

I have limited knowledge of Vico but I do recall that you can apply any number of crews to any one task line.

As I recall if you have resourced the task correctly then by moving the end of the distance line horizontally across the time line the number of crews adjust automatically.

Best regards