UPDATING THE PROGRESS

Member for

14 years

Physical % complete is entered by the user and it implies that when percent complete would not be an accurate measure of real work performed or remaining. Where % complete can be entered by the user or the programme, this is not a real measure.

Physical % complete is preferred over % complete in construction projects where speed of doing the work in activities does not remain same during the activity duration.