Crude Oil Storage Activities and Duration

Member for

11 years 7 months

Guys,

 
Recently we got new EPC project for oil storage tanks and I am shifted to this project.
 
I have experience of oil and gas refinery and exploration
Projects and never did tankage project. 
 
Anyone please send me sample schedule and activities of any EPC Oil storage tanks for my reference purposes.
 
Thanks in advance
 
Regards,
Brijesh
+918003892177

Member for

14 years 11 months

Hi all,

My name is Andronikos and i am currenlty preparing a study about the dangers / risks ascociated with the construction, testing and commisioning of oil tanks / oil - fuel terminals. Dangers related to constructions methods, materials used, substances, etc. 

Therefore i would appreciate if you have any info that will help!

 

Thanks in advance

 

Andronikos

Member for

21 years 8 months

time is of the escence ....



http://www.galglass.co.uk/industrial/pre-cast-concrete-tanks.aspx



Can be manufactured locally just contact any precast facility close to where you are. Precast concrete poured during the day is usually stripped next day, so it shall be strong enough for the worst to happen next day, this is done every day at a precast plant.



Perhaps joint sealant can be critical for this Sika could provide expertise.

Member for

15 years 5 months

Thanks Samer,

I will definitely keep that in mind and will do. If anyone else have anymore tips or possbile go-bys in Primavera that I can take a look at, I welcome it.

I thank you all once again!



All the best,



Kas



ps...sorry Mike, I didn’t pick up on it either (;0)

Member for

17 years 3 months

Dear Kas,



You need to keep close eye about the Electro mechanical requirements especially the testing. Usually, you need special welders.



Also, the you need to discuss scafolding and automatic welding machines.



The best part would be rolling of the plates and achieving the alignment required in the design specifications. Hence, expert construction team is required.



With kind regards,



Samer



PS. Sorry Mike I did not catch up on that :)

Member for

15 years 5 months

Samer, you are correct. Steel is definitely the obvious choice, but I was only throwing the concrete out there due to someone throwing it out during the conversation. I am familiar with the concrete method and know about the since of urgency with working with concrete and all the rebar involved.



I thank you guys once again and if you have any detail information that you would like to provide to fill out what is already been presented it can only assist me more once I get the true SOW and give me some additional ammo once I sit down with the engineers to work out the plan.



All the best,



Kas

Member for

19 years 10 months

Hi Samer



I think you may have realised that the BP storage system was meant to be humorous - I obviously failed completely.



One or two things you forgot on your list:



1. Foundation platform for the steel tank

2. Spillage bund that has to be 120% of the total storage capacity.



Best regards



Mike Testro

Member for

17 years 3 months

Dear Kas,



You are talking about building concrete crude tanks farm for 250,000m3. Say you have 50m dia tank x 10 meters high (4 plates), volume is approximately 20,000m3 and then you need 13 tanks. This is going too expensive and too slow in concrete. Unless there is a specific purpose for that.



If you are worried about sea water and corrosion, then you have paint systems that can provide 10 years warrenty in the most humid areas on earth.



In any event, you job as a planner is to review the Contract Documents, specification and drawings and come up with the best constructable plan with your construction team.



With kind regards,



Samer

Member for

15 years 5 months

Thank you guys so much!!! Yes, the salt caverns have been around for a while (BP Thunderhorse) and are part of the LOOP in storing the oil. The name BP is like mud around here if you mention it get ready for it (;0).



Thanks again and this is very helpful, does anyone have any activity info on the concrete form tanks instead of the steel? Also, it may be nearshore with marine terminal and adding one additional mooring point. I look forward to hearing from you guys, just looking through this site you have some great intellectual conversations and I can’t wait to read and add where ever I can!



Thanks again!!!



Kas

Member for

17 years 3 months

Dear Mike,



If you are talking about the strategic reserve, then that is filling the old wells with the new crude. It has been going on sice Clinton time at least. No need for tanks, the ground in ready to receive the crude.



With kind regards,



Samer

Member for

19 years 10 months

Hi Samer



You must have heard that BP are currently storing massive amounts of Crude Oil in the gulf of Mexico - most of coming right up to Kas front door in the Mississipi.



Best regards



Mike Testro

Member for

17 years 3 months

Dear Mike,



This is interesting to read about. Do you have a link.



Yes you are correct, I am describing the work on a steel tanks farm.



With kind regards,



Samer

Member for

19 years 10 months

Hi Kas



Welocome to PP.



Samer is assuming that the tanks are steel structure.



They may well be slipformed concrete which would require a different set of tasks.



BTW you may have heard that BP have developed their own form of offshore storage round your way.



Best regards



Mike Testro

Member for

17 years 3 months

Dear Kas,



I have done a crude heater in a Refinery and I will provide you with my input regarding what I think might take place on this project.



Project Scope: EPC expansion of 250,000m3 Crude Tanks

1. Engineering

I. Site Survey

II. Calculations and Design Drawings

(Civil, Electrical, Mechanical)

III. Approvals & Review

(Civil, Electrical, Mechanical)

IV. Shop Drawings preparation

(Civil, Electrical, Mechanical)

V. Material Submittals

(Civil, Electrical, Mechanical)

IV. Method Statements submittals and approval

2. Procurement

(Civil, Electrical, Mechanical)

I. Steel Structure Fabrication

II. Steel Tanks Fabrication

III. Floating Steel Roof Fabrication

IV. Steel Painting

V. Steel Delivery to site

3. Construction

Divide into zones, and repeat for each zone

I. Civil Works

II. Anchor Bolt Placing

III. Steel Plates Lifting and Welding in situ

IV. Installation of Steel Roof

V. Erection of secondary structures

VI. Testing of All welds and joints

VII. Air Testing of Tanks/ or per specs

VIII. Final Painting at site.

XI. commissioning

X. Handing Over



It depends on the details of the project that you want to construct. They are the major steps, and you can fill in between the details as per drawings and specifications, evironmental, resources availability, etc.



With kind regards,



Samer