KPI in the Construction Project

Member for

13 years 8 months

Hi,

 Thanks very much for this comment. It help me to think about my ideals.

If you want to get more materials that related to this topic, you can visit: Construction KPIs

Best regards.

Member for

19 years 10 months

Hi The (Olivia Newton or Elton?)

Welcome to Planning Planet - even with a silly name.

It is not good to liven up long dead threads - If you have a point to make or a question to ask then start a new topic in the correct category.

Best regards

Mike Testro

Member for

13 years 8 months

Hi

I read some opinions in this topic. I do not agree above ideal. We can find out some articles at about.com by using Google search.

Member for

15 years 8 months

KPI referred as Key Performance Indicators,are taken as Key Elements of the project which has a greater impact on the project progress and its completion as a whole.These items are so important that they may delay the Project if the execution/Installation of these items are delayed.



Generally KPI are referred to the Bulk materials which has a high value interms of price and runs through the lenght of the project, examples as explained by parvaz: Concrete, Block Works, Steel, Cables, Pipes, Sheet metal works.





hope this serves as solution.

Member for

18 years 8 months

Hi,

As I saw from my clients before I think what your client want is to showing him weekly (or daily) progress of key works , it can be concrete , rebar , form work , cable length , instrument installed , ...



format can be like this :



KPI item -------unit -------Week Planed -------week achived

Conceret -------m3 -------200 ----------------------180

rebar ----------ton ---------2.5------------------------2.2

cable pulling----m---------25000 ------------------24321

Inst. installed---PCS--------- 20 -------------------- 22

Member for

20 years 2 months

Dear Amreshwar,



Meticulous Clients wants their projects delivered efficiently on these three constraints, budget, time and quality. You add safety to the three, then you have something to start with as you KPIs.



Through meetings you should have a feel now what really the Client wants. It’s a good practice just to limit the KPIs in order not to stick his finger in all your works.



A sample for time indicator will be like:



Construction duration at project start = 24 months

Construction duration at current update = 24.5 months

Time predictability = (24.5-24)/24 = 2.1%



Best regards,

R. Catalan

Member for

17 years 3 months

Hi,



I think that you got a lot of good advice until now. You need to give us more description about your project in order to try to assist you more. Here is another answers to the original questions



Q: What are the parameters to define major KPI in the construction project ?

A: PMI has now 44 processes in addition to Health and Safety, Variations, Environmental Impact, Society Impact, etc. All these can be monitored depending on the requirements of the client. If he needs to measure the manhours, then have a KPI for Manhours. Divide the Actual monthly/ Mhrs monthly planned.



Q: How many KPI should we have in a mixed use medium size construction project ?

A: Usually a the clients of a project this size do not ask about KPIs. This person asking about KPIs would have influence from advanced management systems at large corporations.



Q: Owner want to link KPI with cost as well as man hours???

Earned Value Management provides index for the important cost KPIs on the same project. Maybe he wants to compare it to other similar projects! Then you need an external reference.



It is very important to commmunicate with your client to understand exactly what they need to know.



With kind regards,



Samer

Member for

24 years 9 months

Amreshwar,

please think about project success criteria.

What you consider as successful performance?

Minimal problems with quality, being on time and on budget, what else?

KPI shall motivate project participants to improve project success criteria.

There is a problem woth nultiple criteria. Some project may be delayed but saved money - is it good or bad?

There is a need in some overall projec success criterion.

We usually suggest to estimate the cost of one day delay. You can define penalty for poor quakity performance.

If time and quality are estimated in cost units you will have single project success criterion that includes cost, time and quality performance.

It is just an example. Your KPI shall be developed basing on your contract conditions. You can estimate the cost of project time performance if you are motivated to finish earlier. In other case early completion does not bring anything, only delays cost money.

Maybe your Client suggests you to formalize project success criterion to be able to estimate overall project performance.

Best Regards,

Vladimir

Member for

22 years 6 months

Dear Samer,



All above have been set as the major milestones and presented to client in first meeting , but he was insisting on KPI to be defined. In second meeting all other progress measurement coefficient like CPI , SPI ,SV CV etc are provided to him and included in the monthly report.But he is still insisting on KPI’s to be defined for the project. We tried to find out what he is having his mind (he is old experienced civil eng with lots of project management in his hand), but nothing came out of that meeting. He is still asking for "KPI TO BE DEFINED FOR THE PROJECT" with his loud voice in front of CEO , COO etc..



It is not the question of client management but in my views he is looking for something which I am not able to figure out?



Any body else has gone thru the same situation ?



Need advice on this...





Thanks in advance.



Shukla

Member for

22 years 6 months

Dear Samer,



All above has been set as the major milestones and presented to client in first meeting , but he was insisting on KPI to be defined. In second meeting all other progress measurement coefficient like CPI , SPI ,SV CV etc are provided to him and included in the monthly report.But he is still insisting on KPI’s to be defined for the project. We tried to find out what he is having his mind (he is old experienced civil eng with lots of project management in his hand), but nothing came out of that meeting. He is still asking for "KPI TO BE DEFINED FOR THE PROJECT" with his loud voice in front of CEO , COO etc..



It is not the question of client management but in my views he is looking for something which I am not able to figure out?



Any body else has gone thru the same situation ?



Need advice on this...





Thanks in advance.



Shukla

Member for

17 years 3 months

Dear Amreshwar,



You need to know what your client wants to monitor. Then you can make sure that you are satisfying that need. The KPIs for most of the projects are monitoring the completion of the following:



1. Site Set up or mobilization.

2. COC commencement finacial requirements

3. Material submittals (Civil, Architectural, Mechanical, Electrical)

4. Shop drawings (Civil, Architectural, Mechanical, Electrical)

5. Procurmenet

6. Construction

7. Testing and Comissioning

8. Handing over.



At each stage, you can have a KPI to monitor the ratio on a weekly, monthly or total requirements (Completed/Required). All this information can be summarized in one sheet of paper.



Hope that the information helped.



With kind regards,



Samer

Member for

22 years 6 months

Dear Mimoune,



I am working for PMC and having the fully cost & resouces loaded schedule. Client is experienced Civil Engineer and not interested in CPI/SPI ! He is looking for something else...



Any suggestion please??



Thanks in advance..



A.S.Shukla

Member for

19 years

very interesting question, i am waiting to hear from other senior planners what they think.



perhaps you can use earned value method, there is two kpi you can use; cost performance index, and schedule performance index;



cpi= bcwp/acwp

spi =bcwp/bcws



cpi < 1, means that the work cost more then what you have planned.



spi < 1, means that you are late.



now you must be sure what to show to the client, of course never show your "real cost". and i supposed you have a cost loaded program.



please can you be more explicit, your are main contractor ! ?, what’s the type of contract you have lump sum, unit rate, so others can give you better advice.



best regards

Member for

17 years 3 months

Dear Amreshwar,



You need to think about increasing customer satisfaction and reducing cost. So the Parameters that you might consider achieving must be relatd to Cost, Scope, Time and determining what the client values at the start of the project and monitoring that.



With kind regards,



Samer