Planning, Scheduling & Programming Discussion Member for 6 years 11 months Member for 6 years 11 months Submitted by deesanrj66 on Sun, 2018-11-11 05:30 Permalink Hi Balaji,Please refer the Hi Balaji, Please refer the following youtube link regarding Daily Progress Report, which may be useful to you. Also, excel file of daily progress template can be availed. https://youtu.be/TLtZbuA1glY (copy and paste this link in your browser) Best regards, R. Jagadeesan Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2009-02-15 06:30 Permalink RE: Format to track progress Come on Guys This is not a dating agency - please stick to the thread. Best regards Mike Testro Member for 21 years 5 months Member for 21 years 5 months Submitted by Balaji Surendiran on Sat, 2009-02-14 15:26 Permalink RE: Format to track progress Yup ..im from VRCE Nagpur.. Member for 18 years 6 months Member for 18 years 6 months Submitted by PRAKASHCHANDRA… on Sat, 2009-02-14 13:48 Permalink RE: Format to track progress Hi Balaji, R u from VRCE Nagpur? Regards Member for 18 years 6 months Member for 18 years 6 months Submitted by PRAKASHCHANDRA… on Sat, 2009-02-14 13:48 Permalink RE: Format to track progress Hi Balaji, R u from VRCE Nagpur? Regards Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2009-01-10 03:53 Permalink RE: Format to track progress Hi Balaji The quickest way to do it is to put in percentage completions in the column and save each time. Take a small PDA around the site with a spreadsheet of all activities and type in the percentages complete. In P3 these have to be typed in every activity. In PowerProject you can cut and paste from the spreadsheet. Make sure your drop down line is straight - not jagged. Best regards Mike Testro Log in or register to post comments
Member for 6 years 11 months Member for 6 years 11 months Submitted by deesanrj66 on Sun, 2018-11-11 05:30 Permalink Hi Balaji,Please refer the Hi Balaji, Please refer the following youtube link regarding Daily Progress Report, which may be useful to you. Also, excel file of daily progress template can be availed. https://youtu.be/TLtZbuA1glY (copy and paste this link in your browser) Best regards, R. Jagadeesan
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2009-02-15 06:30 Permalink RE: Format to track progress Come on Guys This is not a dating agency - please stick to the thread. Best regards Mike Testro
Member for 21 years 5 months Member for 21 years 5 months Submitted by Balaji Surendiran on Sat, 2009-02-14 15:26 Permalink RE: Format to track progress Yup ..im from VRCE Nagpur..
Member for 18 years 6 months Member for 18 years 6 months Submitted by PRAKASHCHANDRA… on Sat, 2009-02-14 13:48 Permalink RE: Format to track progress Hi Balaji, R u from VRCE Nagpur? Regards
Member for 18 years 6 months Member for 18 years 6 months Submitted by PRAKASHCHANDRA… on Sat, 2009-02-14 13:48 Permalink RE: Format to track progress Hi Balaji, R u from VRCE Nagpur? Regards
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2009-01-10 03:53 Permalink RE: Format to track progress Hi Balaji The quickest way to do it is to put in percentage completions in the column and save each time. Take a small PDA around the site with a spreadsheet of all activities and type in the percentages complete. In P3 these have to be typed in every activity. In PowerProject you can cut and paste from the spreadsheet. Make sure your drop down line is straight - not jagged. Best regards Mike Testro
Member for
6 years 11 monthsHi Balaji,Please refer the
Hi Balaji,
Please refer the following youtube link regarding Daily Progress Report, which may be useful to you. Also, excel file of daily progress template can be availed.
https://youtu.be/TLtZbuA1glY (copy and paste this link in your browser)
Best regards,
R. Jagadeesan
Member for
19 years 10 monthsRE: Format to track progress
Come on Guys
This is not a dating agency - please stick to the thread.
Best regards
Mike Testro
Member for
21 years 5 monthsRE: Format to track progress
Yup ..im from VRCE Nagpur..
Member for
18 years 6 monthsRE: Format to track progress
Hi Balaji,
R u from VRCE Nagpur?
Regards
Member for
18 years 6 monthsRE: Format to track progress
Hi Balaji,
R u from VRCE Nagpur?
Regards
Member for
19 years 10 monthsRE: Format to track progress
Hi Balaji
The quickest way to do it is to put in percentage completions in the column and save each time.
Take a small PDA around the site with a spreadsheet of all activities and type in the percentages complete.
In P3 these have to be typed in every activity.
In PowerProject you can cut and paste from the spreadsheet.
Make sure your drop down line is straight - not jagged.
Best regards
Mike Testro