You can copy and paste to excel the layout that you have in your Project Portfolio or Project Layout then you can do any counting or any formatting on your report. The best and quickest work around on your problem.
Member for
5 years 11 months
Member for5 years11 months
Submitted by Mujtaba Sajjad on Sun, 2021-11-07 11:33
If i type in UDF, it will not show consecutive number after filtering or grouping a specific code. Can we count the specific code in P6 professional and put in reports? This may fulfill the need. For example if i froup the open projects i want to show the numbers against open open project heading like 10 or 20 what so ever.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Sun, 2021-11-07 01:55
Member for
19 yearsHi Mohammad,You can copy and
Hi Mohammad,
You can copy and paste to excel the layout that you have in your Project Portfolio or Project Layout then you can do any counting or any formatting on your report. The best and quickest work around on your problem.
Member for
5 years 11 monthsIf i type in UDF, it will not
If i type in UDF, it will not show consecutive number after filtering or grouping a specific code. Can we count the specific code in P6 professional and put in reports? This may fulfill the need. For example if i froup the open projects i want to show the numbers against open open project heading like 10 or 20 what so ever.
Member for
19 yearsHi Muhammad,Primavera (P6)
Hi Muhammad,
Primavera (P6) has no Auto Number Project Code in the system. The Line number function is only for Activity level.
My alternative solution is to create a Project Users Define Field with integer settings and manually type the numbering system.