Assuming that you have all the settings in place and correct such as maintain and assigned baseline to current project and it was match on the project settings on baseline for earned value calculation, Earned Value calculation was set on Budgeted Value with Planned Date, checked and recalculate cost and total Budget At Completion is correct then the following should have the correct data:
Column to show:
Budget At Completion (BAC) = Baseline labour cost + Baseline non-labour cost + baseline material cost + baseline expenses = Baseline Total Cost
Schedule % Complete = Planned % complete up to the data date (Baseline completion % complete so far)
Plan Value Cost = Budget At Completion * Schedule % Complete (baseline plan value)
Performance % Complete = Percent use to calculate Earned Value (based on the settings technique your project using for computing performance % complete, Activity % Complete by default)
Earned ValueCost = Budget At Completion * Performance % Complete
Actual Cost = labour cost + non-labour cost + material cost + expenses = actual cost to date to data date (manual input)
Cost % Complete = Actual Cost / At Completion Total Cost
Try these columns to show Planned Values (PV) and Earned Values (EV).
Budgeted Total Cost
BL Project Start
BL Project Finish
Start
Finish
Schedule % Complete
Performance % Complete
Planned Value Cost
Earned Value Cost
Schedule Variance
When you say Actual % do you mean the actual cost (such as operating costs, material costs, overheads) that is keyed in by the user, or do you mean the Earned Value, which is auto-calculated by P6 based on the % complete of the activities keyed in by the user
Member for
19 yearsHi Jithin,Assuming that you
Hi Jithin,
Assuming that you have all the settings in place and correct such as maintain and assigned baseline to current project and it was match on the project settings on baseline for earned value calculation, Earned Value calculation was set on Budgeted Value with Planned Date, checked and recalculate cost and total Budget At Completion is correct then the following should have the correct data:
Column to show:
Member for
11 years 5 monthsHi Jithin,Try these columns
Hi Jithin,
Try these columns to show Planned Values (PV) and Earned Values (EV).
When you say Actual % do you mean the actual cost (such as operating costs, material costs, overheads) that is keyed in by the user, or do you mean the Earned Value, which is auto-calculated by P6 based on the % complete of the activities keyed in by the user