It worked - "The Resource Movement Blue Arrows" have appeared - Image Attached.
I had actually accidentially turned on the Resource Group & Sort by Primary Role. Therefore the Tri-State Toggle was alternating only between the first 2 states and not showing the third state i.e. 3 Lines - Indent arrows - Hierarchical Structure.
I did not know that this Column Header is "A Tri-State Toggle".
Thanks A Lot To Both Of You,
With The Very Best Regards.
[[wysiwyg_imageupload:7658:]]
Member for
20 years 6 months
Member for20 years7 months
Submitted by Santosh Bhat on Mon, 2021-03-01 01:53
The Column header for Resource ID is a Tri-State toggle. It can be clicked three times, once for sorting Ascending Alphanumerically, Again for Descending Alphanumerically, and thirdly for Hierarchically based on the Resource Structure.
Make sure you click this three times to go through each option and you should see the indent arrows appear when it is displaying the hierarchical structure.
Look at the Resource ID colum header in the Resource Workspace:
you will see a small symbol on the right side of the header: click on the symbol until you see 3 small lines instead of a triangle; then you will be able to move the resources by using the 4 blue arrow buttons of the tool bar on the right side of the screen
this has nothing to do with User rights, and a stand-alone P6 running with SQLlite database has no access to user rights and profile
Alexandre
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Sat, 2021-02-27 18:26
Look at the Resource ID colum header in the Resource Workspace:
you will see a small symbol on the right side of the header: click on the symbol until you see 3 small lines instead of a triangle; then you will be able to move the resources by using the 4 blue arrow buttons of the tool bar on the right side of the screen
this has nothing to do with User rights, and a stand-alone P6 running with SQLlite database has no access to user rights and profile
Alexandre
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2021-02-26 15:42
The filter is "ALREADY SET TO DISPLAY ALL RESOURCES".
I watched 2 YouTube Videos where the Presentor is also having these arrows grayed out in the video - So I think the Standalone Version seems to have these arrows grayed out - Maybe - I am not sure.
Thanks & Regards.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2021-02-25 14:43
make sure that you have the proper rigth to do this. It is lsited under the Admin Security profiles make sure all of the Has Previleges boxes are checked for whatever profile Name is checked above.
Member for
5 years 8 monthsThanks A Lot To Dear
Thanks A Lot To Dear Mr. Zoltan Palffy too.
With The Very Best Regards.
Member for
5 years 8 monthsDear Mr. Alexandre Faulx-B &
Dear Mr. Alexandre Faulx-B & Mr. Santosh Bhat,
It worked - "The Resource Movement Blue Arrows" have appeared - Image Attached.
I had actually accidentially turned on the Resource Group & Sort by Primary Role. Therefore the Tri-State Toggle was alternating only between the first 2 states and not showing the third state i.e. 3 Lines - Indent arrows - Hierarchical Structure.
I did not know that this Column Header is "A Tri-State Toggle".
Thanks A Lot To Both Of You,
With The Very Best Regards.
[[wysiwyg_imageupload:7658:]]
Member for
20 years 6 monthsVikas, The Column header for
Vikas,
The Column header for Resource ID is a Tri-State toggle. It can be clicked three times, once for sorting Ascending Alphanumerically, Again for Descending Alphanumerically, and thirdly for Hierarchically based on the Resource Structure.
Make sure you click this three times to go through each option and you should see the indent arrows appear when it is displaying the hierarchical structure.
Member for
5 years 8 monthsDear Alexandre Faulx-B,
Dear Alexandre Faulx-B,
[[wysiwyg_imageupload:7656:]]
[[wysiwyg_imageupload:7657:]]
I have pasted 2 Screen Shots of my my Resource ID Column Header.
If I click on the small triangle as shown in the upper image it gives the options as shown in the image &
if I click the small triangle as shown in the below image then P6 just Sorts the Resource ID's columns.
But there is no option where the small triangle changes to 3 lines.
Thanks & Regards.
Member for
5 years 8 monthsDear Alexandre Faulx-B,
Dear Alexandre Faulx-B,
[[wysiwyg_imageupload:7656:]]
[[wysiwyg_imageupload:7657:]]
I have pasted 2 Screen Shots of my my Resource ID Column Header.
If I click on the small triangle as shown in the upper image it gives the options as shown in the image &
if I click the small triangle as shown in the below image then P6 just Sorts the Resource ID's columns.
But there is no option where the small triangle changes to 3 lines.
Thanks & Regards.
Member for
22 years 9 monthsVikas,Look at the Resource ID
Vikas,
Look at the Resource ID colum header in the Resource Workspace:
you will see a small symbol on the right side of the header: click on the symbol until you see 3 small lines instead of a triangle; then you will be able to move the resources by using the 4 blue arrow buttons of the tool bar on the right side of the screen
this has nothing to do with User rights, and a stand-alone P6 running with SQLlite database has no access to user rights and profile
Alexandre
Member for
22 years 9 monthsVikas,Look at the Resource ID
Vikas,
Look at the Resource ID colum header in the Resource Workspace:
you will see a small symbol on the right side of the header: click on the symbol until you see 3 small lines instead of a triangle; then you will be able to move the resources by using the 4 blue arrow buttons of the tool bar on the right side of the screen
this has nothing to do with User rights, and a stand-alone P6 running with SQLlite database has no access to user rights and profile
Alexandre
Member for
16 years 3 monthsno they should not be greyed
no they should not be greyed out I thinks it is a rights issue
go to Secuirty profiles make sure all of the Has Previleges boxes are checked for whatever profile Name is checked above.
Member for
5 years 8 monthsDear Mr. Santosh Bhat,The
Dear Mr. Santosh Bhat,
The filter is "ALREADY SET TO DISPLAY ALL RESOURCES".
I watched 2 YouTube Videos where the Presentor is also having these arrows grayed out in the video - So I think the Standalone Version seems to have these arrows grayed out - Maybe - I am not sure.
Thanks & Regards.
Member for
16 years 3 monthsnot so sure of that
not so sure of that
Member for
20 years 6 monthsZoltan, SQLite databases
Zoltan, SQLite databases don't have any user or security profiles - so those options wont be on the menu.
Its likely becuase the resource view is filtered. Select to display ALL RESOURCES and the arrows will appear.
Member for
16 years 3 monthsREAD MY POST ITS
READ MY POST ITS UNDER
Admin
Security Profiles
Member for
5 years 8 monthsDear Sir,Thanks for your
Dear Sir,
Thanks for your reply.
I am using Primavera Standalone P6 Professional Release - 16.1 with PMDBSQLITE Database
The Admin Menu has only the following options -
1. Admin Preferences
2. Admin Categories
3. Currencies
4. Financial Periods
The other options i.e. -
1. Users
2. Security Profiles
3. Timesheet Dates
ARE MISSING
With Best Regards.
Member for
16 years 3 monthsmake sure that you have the
make sure that you have the proper rigth to do this. It is lsited under the Admin Security profiles make sure all of the Has Previleges boxes are checked for whatever profile Name is checked above.