P6 Professional 16.1 will not add new pred or succ in Window but will using highlight and button combo

Member for

21 years 8 months

Let me know if it doesn't work....  I like new best pals..... 

Member for

12 years 6 months

Genius!  I am not able to verify at this moment but that exactly fits my scenario....Thank you so very much.  In the old days...we would just slowly go insane with these issues, and by old days I mean just prior to your response.  I guess I did not bother seeing if Oracle has a forum, somehow I thought my odds were better here.  Your new best pal, John. 

Member for

12 years 6 months

Genius!  I am not able to verify at this moment but that exactly fits my scenario....Thank you so very much.  In the old days...we would just slowly go insane with these issues, and by old days I mean just prior to your response.  I guess I did not bother seeing if Oracle has a forum, somehow I thought my odds were better here.  Your new best pal, John. 

Member for

21 years 8 months

I think I've answered this before, perhaps in a different forum.  Let me tell you that the same thing happened to me when I was using my laptop with an additional monitor I don't always use.  It appeared that when I went back to using just my laptop monitor, I'd left some of the Primavera windows on the additional monitor, and when I closed they stayed there.  I finally plugged in an addtional monitor again to my laptop and saw my missing detail windows sitting there, patiently waiting for my next action.....

See if this helps....