If you mean the user_setting is corrupted and this resulted in the problem with the layout, you can reset user setting by login to your database and issuing the following command:
update userdata set user_data = ‘null’ where topic_name = ‘pm_settings’;
this will reset user setting back to default setting. I doubt this is the issue as this doesn't reset the layouts. But it worths the shot.
Another option is to delete the user and add a new user as the new user recieves default setting.
Did you try to use one of the default layouts in P6 to see if the problem resolves? The issue might be the corrupted user layout that sometimes happens and only workaround is to built it from scratch.
The WBS corruption is not a usual suspect as normally WBS corruption returns error or makes project invisible.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2017-08-24 14:03
Member for
19 years 4 monthsYes tried using a default
Yes tried using a default layout and still the same. I am just waiting on pemission to gain admin rights and I will then investigate more.
Thanks for your reply.
Member for
13 years 8 monthsIf you mean the user_setting
If you mean the user_setting is corrupted and this resulted in the problem with the layout, you can reset user setting by login to your database and issuing the following command:
update userdata set user_data = ‘null’ where topic_name = ‘pm_settings’;
this will reset user setting back to default setting. I doubt this is the issue as this doesn't reset the layouts. But it worths the shot.
Another option is to delete the user and add a new user as the new user recieves default setting.
Did you try to use one of the default layouts in P6 to see if the problem resolves? The issue might be the corrupted user layout that sometimes happens and only workaround is to built it from scratch.
The WBS corruption is not a usual suspect as normally WBS corruption returns error or makes project invisible.
Member for
16 years 3 monthsthen check the admin rights
then check the admin rights
Member for
19 years 4 monthsThanks Guy's but Id
Thanks Guy's but Id already tried these along with sharing my layout and neither worked. I think it is something to do with user / admin rights.
Member for
13 years 8 monthsGo to View > Group and Sort
Go to View > Group and Sort By >
Uncheck the "Sort bands alphabetically"
Member for
16 years 3 monthsuncheck hide when empty in
uncheck hide when empty in your grouping