Fix earned value at period end

Member for

16 years 3 months

thats if you are using physcial % complete

Member for

9 years 8 months

I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.

Member for

9 years 8 months

I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.

Member for

16 years 3 months

after the update is totally done select tools store period performance 

make sure to set up your financial periods 

Member for

8 years 4 months

I have been advised to do this but when the data date is advanced and the activities progressed the earned value at previous periods is still changed.

Member for

16 years 3 months

tools store period performance