Performance % Complete

Member for

16 years 4 months

yes the Performance percent complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

since there are no resources Ttis just means that there will not be an earned value calculated. You can still have a performance % complete if you look at the duration % complete or the activity % complete  I bet they are the same numbers as the Performance % complete numbers.