Thanks! That definitely gave me a starting point. I exported the date and was able to mess around with pivot tables and conditional formatting to generate something that shows if an activity doesn't have anything tied to its finish. For example, in the screenshot below, activity 1400.7020 has 3 successors, all with SS relationships:
[[wysiwyg_imageupload:4816:]]
I did the same thing for activities with only FF predecessors. Thanks again for the response!
Member for
16 years 4 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2017-05-26 13:18
what you can do is export to excel and only select resources make sure to include realtionship type look of the one that is only SS as the successor now you can filter column C only for SS
Member for
16 years 4 monthsglad I could help but please
glad I could help but please no large pics in the post
Member for
8 years 5 monthsThanks! That definitely gave
Thanks! That definitely gave me a starting point. I exported the date and was able to mess around with pivot tables and conditional formatting to generate something that shows if an activity doesn't have anything tied to its finish. For example, in the screenshot below, activity 1400.7020 has 3 successors, all with SS relationships:
[[wysiwyg_imageupload:4816:]]
I did the same thing for activities with only FF predecessors. Thanks again for the response!
Member for
16 years 4 monthswhat you can do is export to
what you can do is export to excel and only select resources make sure to include realtionship type look of the one that is only SS as the successor now you can filter column C only for SS
[[wysiwyg_imageupload:4815:]]