I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship.
Could you tell me how to avoid changing of dates in this situation?
I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship.
Could you tell me how to avoid changing of dates in this situation?
Member for
16 years 4 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2017-03-16 12:04
Member for
16 years 4 monthsjust filter by wbs and on the
just filter by wbs and on the left use the + and - to roll up and to unroll the procurment activities also in the gropuing select show grand totals
Member for
8 years 8 monthsHi, It is requested to show
Hi,
It is requested to show only procurement activities in P6 and all other ativities should be shown in summary level (wbs level).
I filtered but summary of other activities are shown without date and without gantt chart bar.
Please help me in this case.
Member for
16 years 4 monthsfilter for ALL activities add
filter for ALL activities add a column look under the General Category and bring activity TYPE to the right
on the first activity at the top in the activity type column change it to fixed duration and units/time
now do a fill down in that column
now go to the Projects directory
make sure that your project is highlighted
click the defaults tab and select fixed duration and units/time
done
Member for
8 years 8 monthsHi, Is any body can explain
Hi,
Is any body can explain me about activity code and how to define new project activity codes?
I want to define activity codes to filter easily accordingly.
Member for
8 years 8 monthsHi, How to make Duration %
Hi,
How to make Duration % complete equal to physical % complete in P6?
Then, whenever we enter physical % complete manually, the duration % complete also updated same.
Member for
8 years 8 monthsThank you very much. I got
Thank you very much.
I got it.
Member for
16 years 4 monthschange your duration tyeps to
change your duration tyeps to fixed duration & units/time
Member for
8 years 8 monthsTHANK YOU FOR YOUR ANSWERS. I
THANK YOU FOR YOUR ANSWERS.
I HAVE ANOTHER QUESTION IN P6?
I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship.
Could you tell me how to avoid changing of dates in this situation?
Member for
8 years 8 monthsTHANK YOU FOR YOUR ANSWERS. I
THANK YOU FOR YOUR ANSWERS.
I HAVE ANOTHER QUESTION IN P6?
I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship.
Could you tell me how to avoid changing of dates in this situation?
Member for
16 years 4 monthsgot to tools Global change
got to tools Global change and add a new global change
where physical percent complete is greater than 0
then duration % complete = physical % complete
then execute the global change press change
then committ chnages
do this afret each update after inputting ALL physical % completes
and before you calculate the schedule
Member for
8 years 8 monthsHi to every body, When %
Hi to every body,
When % complete type is physical, how the remaing will be calculated by P6?
Remaining duration I mean after changing of data date and rescheduling???
Member for
8 years 7 monthsexcuse me sir, i,m newbie in
excuse me sir, i,m newbie in this forum. how can i post a question in this forum? thank you
Member for
16 years 4 monthschange the duration type to
change the duration type to fixed duration & units/time for all activities you can add that column duration type then do 1 then do a fill down