How to revise budget unit without changing the current duration???

Member for

16 years 4 months

just filter by wbs and on the left use the + and - to roll up and to unroll the procurment activities also in the gropuing select show grand totals

Member for

8 years 8 months

Hi, 

It is requested to show only procurement activities in P6 and all other ativities should be shown in summary level (wbs level). 

I filtered but summary of other activities are shown without date and without gantt chart bar.

Please help me in this case.  

Member for

16 years 4 months

filter for ALL activities add a column look under the General Category and bring activity TYPE to the right

on the first activity at the top in the activity type column change it to fixed duration and units/time

now do a fill down in that column

now go to the Projects directory

make sure that your project is highlighted

click the defaults tab and select fixed duration and units/time

done

Member for

8 years 8 months

Hi, 

Is any body can explain me about activity code and how to define new project activity codes? 

I want to define activity codes to filter easily accordingly. 

Member for

8 years 8 months

Hi, 

How to make Duration % complete equal to physical % complete in P6?

Then, whenever we enter physical % complete manually, the duration % complete also updated same. 

Member for

16 years 4 months

change your duration tyeps to fixed duration & units/time 

Member for

8 years 8 months

THANK YOU FOR YOUR ANSWERS. 

I HAVE ANOTHER QUESTION IN P6?

I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship. 

Could you tell me how to avoid changing of dates in this situation?

Member for

8 years 8 months

THANK YOU FOR YOUR ANSWERS. 

I HAVE ANOTHER QUESTION IN P6?

I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship. 

Could you tell me how to avoid changing of dates in this situation?

Member for

16 years 4 months

got to tools Global change and add a new global change

where  physical percent complete is greater than 0

then duration % complete  = physical % complete

then execute the global change press change

then committ chnages

do this afret each update after inputting ALL physical % completes

and before you calculate the schedule

 

 

Member for

8 years 8 months

Hi to every body, 

When % complete type is physical, how the remaing will be calculated by P6?

Remaining duration I mean after changing of data date and  rescheduling???

Member for

8 years 7 months

excuse me sir, i,m newbie in this forum. how can i post a question in this forum? thank you

Member for

16 years 4 months

change the duration type to fixed duration & units/time for all activities you can add that column duration type then do 1 then do a fill down