I want to be able to filter out the role and see a stacked histogram of people within that role/discipline.
Right now, I can see stacked histogram by role or stacked histogram by resource but I can't figure out how to filter if I need a certain role broken out by only the people assigned there.
Member for
16 years 4 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2017-03-07 15:17
when you view the resource usage profle NO NOT select the role but the resource name. In the left portion of the resource usage profile you can group and sort on resouce NOT ROLE
Member for
16 years 4 monthsfirst filter for the
first filter for the activities that have the people assigned that you are looking for then
view resource usage profile on the lower portin of the screen on the left hand side select the upside down triangle and select
Select view then by role
Member for
8 years 9 monthsI want to be able to filter
I want to be able to filter out the role and see a stacked histogram of people within that role/discipline.
Right now, I can see stacked histogram by role or stacked histogram by resource but I can't figure out how to filter if I need a certain role broken out by only the people assigned there.
Member for
16 years 4 monthswhen you view the resource
when you view the resource usage profle NO NOT select the role but the resource name. In the left portion of the resource usage profile you can group and sort on resouce NOT ROLE