Oracle Primavera - PM6 Member for 16 years 4 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-02-22 13:23 Permalink that is correct you have to that is correct you have to have these checked to do what you want Member for 18 years 11 months Member for 18 years 11 months Submitted by Eric EVRARD on Wed, 2017-02-22 12:50 Permalink Hi After some search I found Hi After some search I found the tips In the resource window in the details tab simply activate the option "Calculate Costs From Units" for each resource or in the Activity Window under Resource Tab add the column "Calculate Costs from Units" Log in or register to post comments
Member for 16 years 4 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-02-22 13:23 Permalink that is correct you have to that is correct you have to have these checked to do what you want
Member for 18 years 11 months Member for 18 years 11 months Submitted by Eric EVRARD on Wed, 2017-02-22 12:50 Permalink Hi After some search I found Hi After some search I found the tips In the resource window in the details tab simply activate the option "Calculate Costs From Units" for each resource or in the Activity Window under Resource Tab add the column "Calculate Costs from Units"
Member for
16 years 4 monthsthat is correct you have to
that is correct you have to have these checked to do what you want
Member for
18 years 11 monthsHi After some search I found
Hi After some search I found the tips
In the resource window in the details tab simply activate the option "Calculate Costs From Units" for each resource or in the Activity Window under Resource Tab add the column "Calculate Costs from Units"