and Earned Value Management
Assistant Cost Engineer, Turner Construction Co., O'Hare Airport, United Airlines Terminal 1
START Date
END Date
Experience Hours (Forensic Analysis)
5000
Planning Manager, Mott MacDonald Limited (Power Defence Sector), Nuclear New Build and Transmission Projects, Power Generation
START Date
END Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Cost Management)
400
Experience Hours (Forensic Analysis)
200
Principal Planning Engineer, 1) Carillion plc, Kirkintilloch Link Road
START Date
END Date
I was the site Planning Engineer for the Kirkintilloch Link Road, a 4.6Km road valued at £35M reporting directly to the Contracts manager and Commerclai Manager. I developed a fully logic linked cost and resource loaded programme as required by the NEC Contract Conditions for the works which was used both by Carillion and our various client groups for cost and value monitoring and forecasting and has become essential for Cost Index analysis. The programme is also used to demonstrate the effect of compensation events and project manager’s instructions.