What is your preferred method to link a task that starts after the first occurrence of a series of events?
Example - you have a schedule to deliver six widgets A1-A6. After the first widget is delivered a widget support period A7 starts. But you don't know exactly which widget will be delivered first.
How would you link A7 to all six widget deliveries A1-A6 so that its start date always aligns to the earliest delivery? Would this work if another widget is delivered earlier? What would be the logic if A7 was a task dependent activity? What if it was an LOE?
Task ID | Task Name |
A1 | Deliver widget A |
A2 | Deliver widget B |
A3 | Deliver widget C |
A4 | Deliver widget D |
A5 | Deliver widget E |
A6 | Deliver widget F |
A7 | Widget Support Period |