Hi everyone,
Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?
Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in P6 to export file to Excel, then prepare it for importing by coping risks to different activities and return it through import.
I have tried it, but I can not find Risks in Available Options in Export dialogues.
Thank you in advance!