Morning All,
We are currently experiencing a difference between the P6 Server and Stand alone reported Progress on both the Planned and Actaul percentages complete. We have checked that all the Admin Settings and Settings under user preferances are the same.
Has anybody experienced this issue before or know of a solution to get the progress aligned on both the server and stand alone. In terms of the dates we do not have any issues as the Overall and detail task start and finish dates are the same.
Any other additional setting checks that need to be done?
The differences in progress is not major but as mentioned above affects both Planned and Actual Progress. The progress difference varies between 0,50% up to 1,5% in some cases.
Feedback will be appreciated.
Dennis