Hi everyone
We all know that having a negative float means there is a constraint and it affects the EV calculations of LOE activities.
In our company there are two finisg milestones
1- plan completion date
2- contract completuon date
At the begining of the project they are the same and we have a constraint on the second one to be fixed and showing the delays by those negative float.
My boss says this is the best way to show the delays.
Any thoughts and alternatives on that?