Hi
I have been told that when you are doing a monthly update, you shouldn't " schedule" ( F9, I mean) in the middle of update. and you should do all the actualizing and updating and after finishing that, you can " schedule" the project to the new data date , 1st day of next month.
I want to know the reason.
What happens if I press F9 in the middle of the updating and actualizing.