I created a WBS in P6 (8.3 VERSION) exported to a spread sheet as activities settings. then copied the list of activities from another excel file to this spread sheet and specify the WBS name and WBS code for each acvtivity.
While importing it back to P6, i could see all the activities, but not arranged under any specific WBS as above (but only under main Project WBS)
Is there any option to import the WBS also for the activities.
Also, is there any option to change the relationship between activities quickly, for eg: from activity A, there are 50 activities as successor with FS relation. How the relationship can be changed to SS+5 in a easy way.
Regards
Kannan