My ASST SCN has a payrate of $39.62 as diplayed below.

I export the below schedule with the respective activity resource assignments.

The exported TASKRSRC worksheet displays as below.

I import this Excel to a schedule with no resource assignments.

When the Resources and Resource Assignments are imported I get the below.

Why does the Price/Unit import as $1.00/h^?
And I cannot manually change the Price/Unit of Assistant Scientist/A.
The only way to correct the Price/Unit is to delete the resource assignment and re-assign the resource. But this defeats the purpose of importing the Resource Assignmnent from Excel.
Any thoughts?