I am preparing S-Curve for construction project, let's assume the planned progress for the month is 60% and the actual progress is 55%, we are 5% behind. It is not necessary mean that the planned completion date has shifted or should go further?
I think it is not necessary the planned completion date to go further, am I right?
I seriously need your explanation