The fundamental formula for work is:
Work = duration x number of assigned units to the task
So, for example:
Work = 5 days x 3 men = 15 man hours
So work is expressed as man hours (or equipment hours).... is that correct ? Or not?
I ask because in MS project it writes work as hours... not man hours.... that is why I am confused..... which one is correct?