delay claims that push into winter - does the party responsible have to pay for the Winter Ripple effect also? For example, with a bridge deck - original pour in October, owner delay causes pour in November, the deck requires a coating that has a spec requireing 50 degrees and rising - which will not be until Spring, so does the owner have to pay "delay costs, ie overhead" the 3-4 winter months also? I assume in hot locations mayber there is a "not summer" equivalaent - I have mainly worked in cold climates.