I have some historical data relating to weather for a specific region of the uk and am wanting to create a spreadsheet to calculate time risk allowance based on it.
So I can get say pouring concrete TRA each month of the year with the winter months having more time risk or bricklaying, crane down time etc.
Does anyone have an example of something they would use for this?