Hi,
Suppose plan has been created and baselined. Actual data has also been entered.
Now, I realize one particular activity had its start/finish date entered very wrong. Is there a way now to change those planned dates?
thanks
Hi,
Suppose plan has been created and baselined. Actual data has also been entered.
Now, I realize one particular activity had its start/finish date entered very wrong. Is there a way now to change those planned dates?
thanks