Hello everyone,
I'm establishing a schedule for a new project, where I need to assign labor resources by teams.
To simplify the problem, here is a more basic description:
- We're building 10 tanks simultaneously
- Each tank is made of 4 shell rings
- We have 5 teams of welders and scafolders etc..
How to assign these labor resources (welders, scafolders, grinders...) while keeping their own team assignment (T1, T2...T5)?
I'll need to visualize team activity as a function of Time in order to plan their deployment.
I hope I explained my problem well. If not, I'll be happy to clarify more.
Thanks in advance.
Regards
Hamza