Why do schedulers put cost in as a resource called cost instead of using the cost fields? I have seen many schedules over the years and I have seen that quite a bit. Also, I work in a corporate system where we are supposed to stick to "Project Calendars" but I noticed that resources have to have a calendar and they apear to only use the Global Calendars - is there a work-around, is that correct?