Hi Experts,
One of my clients requesting activity split relationship in P6, for example, we have three activities A, B, C. After activity A progressed 20%, activity B has to start and after completion of activity A, C has to start. I recommended my client to Split the activity A into two activities like activity A (Initial) and activity A (Final). After completion of activity A (initial), activity B can start and after completion of activity A(Final), activity C can start. Any other way to show this activity midway relationship in P6?