Dear all,
I am just checking on the actual data input in Spider, which is a bit different from MS Project and Primavera.
Soppuse activity started a bit not when it was supposed to start and / or finished a bit later. How do I enter actual start and actual finish? I do not see columns for actual start and actual finish