Hi guys!
I tried to look it up on forum, but it didn't work out for me.
My question is:"How to assign some particular resource to the activity without MSP distributing its quantity by number of days, but showing the assigned quantity every day of activity duration?"
In my particular case it is formwork with many different solutions which I count in pieces, but in the tasks with a different durations. Multiplying the quantity with number of days would solve the problem, but i would prefer more "elegant" solutions, because I have many repetitions with same/similar quantities, but different durations.