Hi,
Im having a weird issue whereby I am exporting an XER of a project that has been progressed, changing it to a .txt file then opening it in Excel to "bulk add" activity codes. I then save the file, change it back to an xer and import the project.
Everything works perfectly APART from the schedule now has no progress. Logic remains the same, new activity codes are there - everything is good except all progress has reset back to 2010!
Ive since checked the .txt file and the export does contain all the correct dates for Act Start/finish etc etc - but for some reaon these are getting lost during import?
Any ideas?
Phil.