Dear All,
Hope you are doing great!
I have few queries related to resource loading:
1. Let's say there is an activity (duration 1 day) which required 10 welders and 5 helpers. So how to assign resources to the activites. Do I have to define 10 welders and 5 fitter in the resources tab? What I did was I defined 1 welder and 1 fitter as labor resource and then mannually entered budgetted workhours corresponding to 10 welder (10 nos. x 10 hrs/day = 100 hrs) and 5 fitters (50 hrs) respectively. But if I see the manpower allocation, it shows welder and fitter are overallocated which is obvious. So what is the better way of doing this?
2. Is there is any option in P6 which allow to enter construction qunatities (for construction activities)...example Piping Erection (Scope 10000 IM, Act: 2500 IM).
3. Is there is any option in P6 where we can define the productivity so that P6 itself calculate the required Workhours/ Manpower.