Hi Schedule Experts,
Just to pick up your brain a bit; what is the best automatic method to identify second, third, fourth etc. Longest Path's in Primavera P6? I have a complex schedule with many constraints and resource levening and unfortunately the traditional way of using float path view with F9 settings of selecting a ending activitiy does not quite work in P6 for me. Is there any other application or in P6 itself where I can import XER file and application identify the first 5 longest path's for the project in order? There has to be something cause P6 float path does not work the best. (I am not so worried about leveling so can take that off as well). This is for evaluation of cuncurrent delays from Contractor or owner at anytime or in any update.
Thanks, Sean