Hi ...
How to deal with "Out of sequences / Hangers" while tracking the project? I know how to find, but i just want to know how to fix it without changing the baseline end date?
Please note, ours a simple duration tracking project, without any resource/cost loading on it. Since we are not changing the end date, we dont require to do any RA & Stake holders approval. its a simple bug fixing. i would like to know how to correct it.