In the screen shot below, i have applied 7 days work week for project duration activity, start miletone and finish milestone , for all other its 6 days work week calender. On the overall summary level original duration is '959 days' , even though activity project duration is of duration 1095 days. i want to show original duration for project as 1095 days.