Dear All;
i have a question about milestone that i want to see if its should be done in 2 months could be warned by ms project?
for example: i have a summary task that building reinforced concrete works, and i linked this after a "rebar procurement" milestone. the thing that i want to do is, can i make ms project put a flag or warning before 2 months left to this milestone, so i can warn my manager about "we should supply rebar in 2 months".
Thanks