Submitted by PRASAD KUKUNURI on Thu, 2019-01-10 11:50
Hello frineds, |
|
Hope you all are doing great. |
I Have construction Acitivtes (Physical %) which are assinged with labor Units (Direct) & Cost not loaded. That means during the update of scheudle I will have BL Units, Planned Units, Earned Units. Now I would like to see Activity Plan % & Earned % at the activity level, WbS & SubWBS level also. |
So, I have created One UDF as integer and I applied the Global change |
UDF = Planned units/BL Units * 100%; This is successed for Acitivity level. But How to get the Plan % & Earned % at the WBS Level ? |
|
Finally My goal is see the Plan % & Earned % at the Acitivy & WBS level also. |
|
Hope I have cleared myself. |
|
Thanking you. |
|
Prasad - |
prasad.e3@gmail.com |