Hello Vladimir,
Materials in Spider have an option called Discrete Consumtion which rounds up the consumtion of the material (granted the Backload consuption is set to No).
So here is my question, is there a way to do this with resources?
Example:
Backhoe is paied by the day even if it works for 2 hours or for 8. I would like to know if there is a way to take this into account when calculating costs.
Best regards,
Bogdan