RoSE 1 Phase II
- Gross(baseline,status,recovery) weekly Status and recovery weekly from Jan –Oct, monthly from Oct- Present.
- Summary Target(baseline,status,recovery) monthly status and update before and detailed Target weekly developed.
- Detailed NETT(baseline,status,recovery) weekly status and modify
- Progress curve, project completed percentage developed for monthly report.
- Subcontractor’s overall schedule review and combined.
- What- if schedule for several option such as Roof detailed,L1 Slab etc.
- 2 weekly schedule weekly development/ other short range schedule such as shop drawing.
- Incentive milestone schedule development as required.
- Sub-contract programming requirement sheet development
- Delay Register update as required.
- Monthly report–schedule part,3 monthly move in schedule, Site progress photo-weekly.
- Project review documents –schedule part MSD
MSD Phase II & HHTR schedule draft (Gross, target and NETT) RoSE 1 Phase I
11 Medium range schedule development and daily trace such as Asbestos removal,roof,basement,as built drawings handover.