START Date:
January, 2014
END Date:
December, 2015 1 review area schedule
- develop weekly#monthly#yearly schedule
- trace project progress and give advice for delay activity. 4 review working plan
5 have weekly pull planning/progress meeting 6 study contract, shop drawing, specification
- development of WBS code, engineering, procurement, construction, commissioning, authority and facade area development, civil structure, MEP kitchen, elevator schedule
- level 1 milestone to level 4 schedule development and review General contractor level 4 schedule resources leveling for facade schedule.
- engineering schedule, add more critical item, such a sample, mockup, purchase order, delivery, filed need date
- check list development "dust free", ride complete checklist, "ready for show " etc...
- 13earn value, critical path, in progress activity, float path#bar chart
- monthly report, manpower chart, equipment chart, obs,
- excel format for daily report
- project complete percentage.