It seems that Activity baseline data is connected to "task_code" when it used to be connected to "task_id" in the past. That used to mean that you could change what we see as the "Activity ID" and P6 still kept the relevant baseline data (dates etc). Now, if you change an Activity ID, you lose the baseline data. If you swap activitiy ID's between two different activities, the baseline data swaps too. This doesn't seem right to me. Is there a way to change this?