I have been trying for the last hour to update a baseline schedule, but everytime I assign it to my current schedule the baseline dates are incorrect.
Even when I delete the baseline I still have a baseline start, finish etc. I've tried creating a new baseline and even that didn't work.
So I have an activity with Start Date 6th August, but a Baseline Start of 28th May. I want my baseline date to equal the current planned start date. There is no baseline currently assigned to the schedule but I still have a baseline start?
Any help would be greatly appreciated.
Thanks