I am creating a 24 hour Shutdown schedule.Now I Resources are being assigned. There are two working shiftsin this Shutdown first shift- 7Am to 7pm and second shift 7Pm to 7 am.
My question is Is it necessary to create two shifts for each resource, when the price per unit is same?
May be, I would be asked to put 12 manpower in day and 8 in night so how to assign resource in this case ? Can anyone guide please ? Regretfully I am not good when it comes to use resources in P6.